NMIA Milestones

12th October

2024

Indian Air Force (IAF) C-295 aircraft successfully conducted an inaugural landing on the South runway

26

NMIAL signed an agreement with Munich Airport for supporting its in the ORAT process

29th August

2024
25

18th July

2024

NMIAL in collaboration with the Airports Authority of India (AAI) initiated flight calibration process on its South Runway 08/26

24

NMIA received permanent power by comissioning its Receiving Sub-Station (RSS) and Distribution Sub-Station (DSS)

11th June

2024
23

22nd May

2024

International Air Transport Association (IATA) assigned the location Code 'NMI' to NMIA.

22

NMIA commences Roof Lining (Liner Fixing) work of the Passenger Terminal Building

27th October

2023
21

17th August

2023

International Civil Aviation Organisation (ICAO) alloted 4 letter location indicator Code 'VANM' to NMIA

20

NMIAL completed the construction of the first slab of Terminal 1 headhouse basement

18th February

2023
19

30th March

2023

NMIAL commenced construction of its first mega column of the Passenger Terminal Building

18

NMIAL conducted pooja ceremony for the First Mega Column footing

27th November

2022
17

11th June

2022

CIDCO handed over the entire 1160Ha of Airport site to NMIAL

16

Financial closure achieved for NMIA Project with the execution of financing documents with the State Bank of India (SBI)

30th March

2022
15

5th August

2021

Post change in management control, NMIAL commenced work on site

14

AAHL took over management control of Mumbai International Airport Limited (MIAL), through which it also took control over NMIAL

8th July

2021
13

2nd December

2021

Environmental and CRZ Clearance granted to NMIA project with NMIAL as project proponent by Ministry of Environment Forest and Climate Change (MoEF & CC)

12

NMIAL awards EPC contract to Larsen & Toubro (L&T)

1st September

2019
11

15th May

2019

NMIAL submits Final Master Plan to CIDCO

10

NMIAL was granted in principle approval from Directorate General of Civil Aviation (DGCA) for construction of the Airport

29th August

2018
09

8th July

2018

CIDCO provided 90% 'Right Of Way' (ROW) to NMIAL

08

At the ground ceremony Prime Minister Shri. Narendra Modi unveiled the foundation plaque for the Navi Mumbai International Airport

19th February

2018
07

9th January

2018

Navi Mumbai International Airport Pvt. Ltd. (NMIAL) signed the Concession Agreement with CIDCO for the Navi Mumbai International Airport project

06

MIAL submitted Initial Master Plan (IMP) for NMIA to CIDCO, as per conditions of Concession Agreement

25th November

2017
05

26th October

2017

CIDCO awarded the NMIA Project to Mumbai International Airport Ltd. (MIAL)

04

Mumbai International Airport Ltd (MIAL), was declared the winning bidder for the Navi Mumbai International Airport Project (NMIA)

14th February

2017
03

1st October

2016

Commencement of predevelopment work by CIDCO

02

Global Tender Floated by CIDCO for appointment of concessionaire for Navi Mumbai International Airport on Design, Built, Finance, Operate and Transfer (DBFOT) Basis

11th February

2016
01

Our Milestones - A Glimpse

img
img
img
img
img
img

Indian Air Force Officers after successfully landing a C-295 aircraft.

Indian Air Force Officers after successfully landing a C-295 aircraft.

Water cannon salute to C-295 IAF Aircraft post its successful inaugural landing on the South runway

Initiation of Roof Lining Installation at the Passenger Terminal Building

Commencement of First Mega Column work at the Passenger Terminal Building

Financial closure successfully achieved for the Navi Mumbai International Airport Project.